Here’s a frequently asked question in the SAFe community: I wanted to understand what SAFe says about someone who wants to go faster than 2 weeks of iteration? I mean the whole PI concept is based on 5 iterations worth of planning. What if a team/organization wants to develop and synchronize faster than 2 weeks? Is speed going to be compromised by following the standards of PI cadence?

Here’s my take:

Adjusting Cadence Length in SAFe – Can you? Should you?

SAFe considers the 2-week iteration length as a default rather than a rule.

The question you need to consider is what inspection and adaptation cycle you’re looking to accelerate – the Iteration or the PI.

Basically, do you want an opportunity to tactically adjust priorities more frequently than every 2w? Or do you want to adjust a more strategic direction more often than every 8-12w?

With the answer to that, you can experiment either with iteration length and/or PI length. Of course, the cadence length affects coordination overhead – there’s a fine balance.

Additionally, we’re talking about a Planning, Inspection, and Adaptation cadence – NOT the release cadence. Releases are on-demand meaning can be more frequent (or less).

Iteration Goals and PI Objectives provide us with room to maneuver

Another point to remember is that you can adjust iteration backlogs as long as you’re focusing on iteration goals. And even PI objectives can be adjusted – “Assume Variability Preserve Options”. If it’s occasional adjustment it’s not a reason to necessarily use a faster cadence.

Is team-level Kanban the solution to the need for more flexibility in SAFe?

Many teams think Kanban might be the best choice for them if they need more and more flexibility. Kanban CAN be a better fit if your demand is extremely volatile. I would be very careful though. Doing some level of goal-setting and prioritization and planning on a cadence is a powerful way for a team to focus. Do we really WANT to be a strictly reactive team?

Kanban combined with flexibility with some of the capacity we have each iteration can definitely be helpful and is why we recommend all Agile Teams in SAFe use Kanban to limit their WIP and improve their flow – this actually enables them to change scope even within an Iteration if that’s needed in order to achieve their Goal. (see my recent blog post that talks about dynamic scope in SAFe).

“Kanban Teams” in SAFe have an iteration cadence with the establishment of iteration goals even if not detailed iteration backlogs. Maybe that’s a good fit for your context maybe not. It might be an interesting experiment to try.

What if Planning a PI doesn’t make sense?

Finally, if PI planning doesn’t make sense even if PI is shorter – maybe you need to reflect on SAFes appropriateness for your context or on what’s so volatile about the demand coming your way and whether it’s “nature of the beast” or a systemic impediment to work on …

What’s the Bottom Line

What I tried to show here is that a conversation about what to do when the iteration feels too long should start with “Why”. Get to the bottom of what’s currently not ideal, look at the different options, consider Lean, Agile, and SAFe principles, and figure out whether it makes sense to change the cadence, change your approach to the balance between planning and flexibility, the difference between committing to goals and committing to backlogs, and the role that more flow-oriented techniques such as Kanban can play in addressing your issue.

Interested to hear any thoughts or experiences. Leave us a comment !

Subscribe for Email Updates:

Categories:

Tags:

Agile Games and Exercises
Professional Scrum with Kanban
SAFe DevOps
Advanced Roadmaps
Kaizen
AgileSparks
Agile in the Enterprise
RTE
Limiting Work in Progress
Business Agility
Perfection Game
Scrum With Kanban
System Integration Environments
Continuous Integration
Agile Testing Practices
Lean-Agile Budgeting
POPM
SA
Lean and Agile Techniques
Certification
Lean Agile Organization
Pomodoro Technique
ATDD vs. BDD
Principles of Lean-Agile Leadership
Agile Product Ownership
Continuous Deployment
Agile Games
RTE Role
Kanban
lean agile change management
Software Development Estimation
Manage Budget Creation
Frameworks
Nexus and Kanban
Jira Plans
Presentation
Continuous Planning
Built-In Quality
speed at scale
ATDD
Agile Delivery
Accelerate Value Delivery At Scale
Agile Israel
Rapid RTC
Professional Scrum Master
Planning
Agile Project
Jira admin
Agile Exercises
Kanban Game
Nexus
Agile Risk Management
Agile Assembly Architecture
Agile Contracts Best Practices
Introduction to Test Driven Development
Lean-Agile Software Development
ROI
Agile Basics
BDD
Elastic Leadership
AI Artificial Intelligence
Nexus Integration Team
Lean Agile Management
Implementing SAFe
Quality Assurance
Self-organization
Introduction to ATDD
Continuous Delivery
Acceptance Test-Driven Development
Legacy Code
Product Ownership
SAFe
Lean Startup
Agile Community
Implementation of Lean and Agile
Achieve Business Agility
Sprint Retrospectives
Systems Thinking
Risk Management on Agile Projects
Agile Release Management
IT Operations
Lean and Agile Principles and Practices
Atlassian
Managing Risk on Agile Projects
Nexus vs SAFe
Covid19
Artificial Intelligence
Games and Exercises
Scaled Agile Framework
Agile India
WIP
Sprint Planning
System Archetypes
Atlaassian
Agile Development
Lean Agile Leadership
Scrum Master
Kanban Kickstart Example
Hybrid Work
LAB
Scrum Values
A Kanban System for Software Engineering
Agile Product Development
Risk-aware Product Development
GanttBan
QA
Legacy Enterprise
LeSS
NIT
PI Objectives
Lean Software Development
Kanban 101
predictability
The Agile Coach
Entrepreneurial Operating System®
Managing Projects
Tips
Tools
Operational Value Stream
Kaizen Workshop
An Appreciative Retrospective
Agile for Embedded Systems
ART Success
Lean Agile Basics
Product Management
EOS®
Development Value Streams
Agile Project Management
The Kanban Method
Agile Techniques
Iterative Incremental Development
Jira
Test Driven Development
Kanban Basics
LPM
Scrum Primer
Effective Agile Retrospectives
Agile Release Planning
DevOps
Portfolio for Jira
SAFe Release Planning
Coaching Agile Teams
speed @ scale
Video
Webinar
Professional Scrum Product Owner
Large Scale Scrum
Program Increment
Lean Agile
Value Streams
Engineering Practices
TDD
What Is Kanban
System Team
Process Improvement
Jira Cloud
Agile Israel Events
Daily Scrum
Code
PI Planning
Continuous Improvement
agileisrael
RSA
Story Slicing
Risk Management in Kanban
Agile
Scrum and XP
Release Train Engineer
Enterprise DevOps
Agile Mindset
Applying Agile Methodology
Lean Budgeting
Scrum
Scrum Guide
Agile Outsourcing
Software Development
ARTs
Sprint Iteration
Scrum Master Role
Reading List
Certified SAFe
AI
Releases Using Lean
Change Management
Agility
Scrum.org
Agile Program
Slides
ALM Tools
Lean Risk Management
ScrumMaster Tales
SPC
Spotify
Agile and DevOps Journey
Amdocs
Agile Marketing
AgileSparks
Logo
Enable registration in settings - general

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart