Here’s a frequently asked question in the SAFe community: I wanted to understand what SAFe says about someone who wants to go faster than 2 weeks of iteration? I mean the whole PI concept is based on 5 iterations worth of planning. What if a team/organization wants to develop and synchronize faster than 2 weeks? Is speed going to be compromised by following the standards of PI cadence?

Here’s my take:

Adjusting Cadence Length in SAFe – Can you? Should you?

SAFe considers the 2-week iteration length as a default rather than a rule.

The question you need to consider is what inspection and adaptation cycle you’re looking to accelerate – the Iteration or the PI.

Basically, do you want an opportunity to tactically adjust priorities more frequently than every 2w? Or do you want to adjust a more strategic direction more often than every 8-12w?

With the answer to that, you can experiment either with iteration length and/or PI length. Of course, the cadence length affects coordination overhead – there’s a fine balance.

Additionally, we’re talking about a Planning, Inspection, and Adaptation cadence – NOT the release cadence. Releases are on-demand meaning can be more frequent (or less).

Iteration Goals and PI Objectives provide us with room to maneuver

Another point to remember is that you can adjust iteration backlogs as long as you’re focusing on iteration goals. And even PI objectives can be adjusted – “Assume Variability Preserve Options”. If it’s occasional adjustment it’s not a reason to necessarily use a faster cadence.

Is team-level Kanban the solution to the need for more flexibility in SAFe?

Many teams think Kanban might be the best choice for them if they need more and more flexibility. Kanban CAN be a better fit if your demand is extremely volatile. I would be very careful though. Doing some level of goal-setting and prioritization and planning on a cadence is a powerful way for a team to focus. Do we really WANT to be a strictly reactive team?

Kanban combined with flexibility with some of the capacity we have each iteration can definitely be helpful and is why we recommend all Agile Teams in SAFe use Kanban to limit their WIP and improve their flow – this actually enables them to change scope even within an Iteration if that’s needed in order to achieve their Goal. (see my recent blog post that talks about dynamic scope in SAFe).

“Kanban Teams” in SAFe have an iteration cadence with the establishment of iteration goals even if not detailed iteration backlogs. Maybe that’s a good fit for your context maybe not. It might be an interesting experiment to try.

What if Planning a PI doesn’t make sense?

Finally, if PI planning doesn’t make sense even if PI is shorter – maybe you need to reflect on SAFes appropriateness for your context or on what’s so volatile about the demand coming your way and whether it’s “nature of the beast” or a systemic impediment to work on …

What’s the Bottom Line

What I tried to show here is that a conversation about what to do when the iteration feels too long should start with “Why”. Get to the bottom of what’s currently not ideal, look at the different options, consider Lean, Agile, and SAFe principles, and figure out whether it makes sense to change the cadence, change your approach to the balance between planning and flexibility, the difference between committing to goals and committing to backlogs, and the role that more flow-oriented techniques such as Kanban can play in addressing your issue.

Interested to hear any thoughts or experiences. Leave us a comment !

Subscribe for Email Updates:

Categories:

Tags:

Agile for Embedded Systems
Lean Startup
Agile Product Development
Amdocs
Story Slicing
Scrum Primer
Lean and Agile Techniques
Scaled Agile Framework
Manage Budget Creation
Test Driven Development
Introduction to ATDD
Acceptance Test-Driven Development
Jira
System Team
Tools
Lean Agile Basics
Agile Program
Professional Scrum Product Owner
Planning
Spotify
Daily Scrum
Elastic Leadership
Sprint Planning
SA
Managing Projects
Professional Scrum with Kanban
Games and Exercises
Jira admin
Agile Israel
System Archetypes
Risk Management on Agile Projects
Principles of Lean-Agile Leadership
Agile Release Planning
Agile Techniques
Scrum With Kanban
Scrum Master Role
Iterative Incremental Development
ATDD vs. BDD
Agile Community
Lean Agile Leadership
LPM
AgileSparks
Nexus vs SAFe
speed at scale
Webinar
Agile Basics
Risk-aware Product Development
Product Management
Release Train Engineer
Lean Budgeting
Continuous Planning
Effective Agile Retrospectives
speed @ scale
Change Management
Presentation
Agile Development
Managing Risk on Agile Projects
System Integration Environments
SAFe DevOps
Legacy Enterprise
Operational Value Stream
Portfolio for Jira
Process Improvement
Rapid RTC
Implementing SAFe
Lean-Agile Software Development
Kaizen Workshop
LAB
Scrum.org
Code
Nexus and SAFe
Kanban Kickstart Example
Legacy Code
Agile Marketing
Pomodoro Technique
Team Flow
Professional Scrum Master
Lean Risk Management
Perfection Game
User stories
ART Success
Coaching Agile Teams
POPM
PI Objectives
Artificial Intelligence
PI Planning
An Appreciative Retrospective
Sprint Retrospectives
Systems Thinking
LeSS
Agile in the Enterprise
Agile Project
Continuous Delivery
Quality Assurance
ALM Tools
Lean-Agile Budgeting
Hybrid Work
Covid19
Implementation of Lean and Agile
EOS®
Agile Project Management
Achieve Business Agility
RTE Role
Agile
Nexus and Kanban
Keith Sawyer
Agile Games and Exercises
Accelerate Value Delivery At Scale
Agile Risk Management
Agility
Lean Agile Management
Built-In Quality
Engineering Practices
Agile Games
Applying Agile Methodology
Risk Management in Kanban
chatgpt
Self-organization
SPC
Agile Israel Events
Kanban Game
Atlassian
Atlaassian
A Kanban System for Software Engineering
Entrepreneurial Operating System®
Scrum and XP
BDD
DevOps
lean agile change management
Kanban 101
Reading List
WIP
ROI
Certified SAFe
Scrum Guide
IT Operations
Agile Contracts Best Practices
Slides
Advanced Roadmaps
Sprint Iteration
Scrum Values
Kanban Basics
Video
Retrospectives
Certification
transformation
Continuous Integration
Tips
Continuous Improvement
Limiting Work in Progress
Nexus
Continuous Deployment
RTE
Value Streams
Kanban
GanttBan
What Is Kanban
Lean Agile
Agile India
TDD
SAFe Release Planning
Scrum
Agile Outsourcing
AI Artificial Intelligence
Agile Release Management
Lean Software Development
Agile Mindset
ATDD
The Agile Coach
Program Increment
Business Agility
ARTs
Lean Agile Organization
AI
Product Ownership
Nexus Integration Team
Scrum Master
SAFe
Frameworks
NIT
Jira Plans
Enterprise DevOps
Large Scale Scrum
Development Value Streams
Kaizen
RSA
Agile Product Ownership
ScrumMaster Tales
Agile Exercises
Agile and DevOps Journey
Agile Testing Practices
Lean and Agile Principles and Practices
Jira Cloud
Introduction to Test Driven Development
Agile Delivery
Releases Using Lean
Software Development
The Kanban Method
Software Development Estimation
agileisrael
predictability
QA
AgileSparks
Logo
Enable registration in settings - general

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart