Here’s a frequently asked question in the SAFe community: I wanted to understand what SAFe says about someone who wants to go faster than 2 weeks of iteration? I mean the whole PI concept is based on 5 iterations worth of planning. What if a team/organization wants to develop and synchronize faster than 2 weeks? Is speed going to be compromised by following the standards of PI cadence?

Here’s my take:

Adjusting Cadence Length in SAFe – Can you? Should you?

SAFe considers the 2-week iteration length as a default rather than a rule.

The question you need to consider is what inspection and adaptation cycle you’re looking to accelerate – the Iteration or the PI.

Basically, do you want an opportunity to tactically adjust priorities more frequently than every 2w? Or do you want to adjust a more strategic direction more often than every 8-12w?

With the answer to that, you can experiment either with iteration length and/or PI length. Of course, the cadence length affects coordination overhead – there’s a fine balance.

Additionally, we’re talking about a Planning, Inspection, and Adaptation cadence – NOT the release cadence. Releases are on-demand meaning can be more frequent (or less).

Iteration Goals and PI Objectives provide us with room to maneuver

Another point to remember is that you can adjust iteration backlogs as long as you’re focusing on iteration goals. And even PI objectives can be adjusted – “Assume Variability Preserve Options”. If it’s occasional adjustment it’s not a reason to necessarily use a faster cadence.

Is team-level Kanban the solution to the need for more flexibility in SAFe?

Many teams think Kanban might be the best choice for them if they need more and more flexibility. Kanban CAN be a better fit if your demand is extremely volatile. I would be very careful though. Doing some level of goal-setting and prioritization and planning on a cadence is a powerful way for a team to focus. Do we really WANT to be a strictly reactive team?

Kanban combined with flexibility with some of the capacity we have each iteration can definitely be helpful and is why we recommend all Agile Teams in SAFe use Kanban to limit their WIP and improve their flow – this actually enables them to change scope even within an Iteration if that’s needed in order to achieve their Goal. (see my recent blog post that talks about dynamic scope in SAFe).

“Kanban Teams” in SAFe have an iteration cadence with the establishment of iteration goals even if not detailed iteration backlogs. Maybe that’s a good fit for your context maybe not. It might be an interesting experiment to try.

What if Planning a PI doesn’t make sense?

Finally, if PI planning doesn’t make sense even if PI is shorter – maybe you need to reflect on SAFes appropriateness for your context or on what’s so volatile about the demand coming your way and whether it’s “nature of the beast” or a systemic impediment to work on …

What’s the Bottom Line

What I tried to show here is that a conversation about what to do when the iteration feels too long should start with “Why”. Get to the bottom of what’s currently not ideal, look at the different options, consider Lean, Agile, and SAFe principles, and figure out whether it makes sense to change the cadence, change your approach to the balance between planning and flexibility, the difference between committing to goals and committing to backlogs, and the role that more flow-oriented techniques such as Kanban can play in addressing your issue.

Interested to hear any thoughts or experiences. Leave us a comment !

Subscribe for Email Updates:

Categories:

Tags:

Coaching Agile Teams
Continuous Deployment
Scrum Guide
Business Agility
Agile Israel Events
Kanban Kickstart Example
PI Planning
Jira Cloud
ROI
Professional Scrum Product Owner
Applying Agile Methodology
Lean-Agile Software Development
Code
Keith Sawyer
Pomodoro Technique
Games and Exercises
Kanban
Agile Techniques
Nexus and Kanban
Kanban Basics
Jira admin
Agile in the Enterprise
Continuous Improvement
Operational Value Stream
User stories
agileisrael
Presentation
Agile Project
SAFe Release Planning
Achieve Business Agility
NIT
Legacy Code
Managing Risk on Agile Projects
Video
Agile and DevOps Journey
EOS®
Spotify
Frameworks
Accelerate Value Delivery At Scale
Agile Release Planning
Agile Risk Management
Kaizen Workshop
Professional Scrum with Kanban
Daily Scrum
Continuous Integration
Lean Budgeting
Continuous Planning
ARTs
Agile Product Development
Agile
Team Flow
Agile Assembly Architecture
Built-In Quality
Continuous Delivery
Nexus vs SAFe
Sprint Planning
Jira
Agile Games
Lean Agile Basics
Risk Management in Kanban
TDD
lean agile change management
Jira Plans
Scrum Values
Advanced Roadmaps
Agile Testing Practices
Legacy Enterprise
Agile Development
WIP
LAB
Scrum and XP
Risk-aware Product Development
speed at scale
Lean Risk Management
Scrum With Kanban
Sprint Retrospectives
ALM Tools
Sprint Iteration
ATDD vs. BDD
System Integration Environments
SA
Agile for Embedded Systems
Lean Startup
Nexus and SAFe
Agile Exercises
Systems Thinking
Scrum Master
RTE
Lean and Agile Principles and Practices
DevOps
PI Objectives
Product Management
SPC
predictability
POPM
GanttBan
Lean-Agile Budgeting
Software Development Estimation
Agile Community
Lean and Agile Techniques
AI
The Agile Coach
Kanban 101
Releases Using Lean
ART Success
Story Slicing
LPM
Product Ownership
Agility
Nexus
Iterative Incremental Development
Perfection Game
Scrum Master Role
Entrepreneurial Operating System®
Covid19
Release Train Engineer
Reading List
Tools
Acceptance Test-Driven Development
Agile Outsourcing
Portfolio for Jira
RSA
SAFe
BDD
Rapid RTC
Agile Basics
SAFe DevOps
Scrum.org
Quality Assurance
Agile India
Change Management
What Is Kanban
Agile Mindset
Agile Games and Exercises
Limiting Work in Progress
Hybrid Work
System Archetypes
Webinar
The Kanban Method
ScrumMaster Tales
Implementation of Lean and Agile
Agile Release Management
Agile Program
AI Artificial Intelligence
Slides
Large Scale Scrum
Program Increment
Engineering Practices
Self-organization
LeSS
Introduction to Test Driven Development
IT Operations
Effective Agile Retrospectives
Tips
Scaled Agile Framework
Manage Budget Creation
Introduction to ATDD
speed @ scale
Certified SAFe
ATDD
Value Streams
Agile Contracts Best Practices
AgileSparks
A Kanban System for Software Engineering
Scrum
Implementing SAFe
Amdocs
Lean Software Development
Kanban Game
Agile Marketing
System Team
Nexus Integration Team
Kaizen
Lean Agile Management
Agile Project Management
Lean Agile Organization
Lean Agile Leadership
Agile Israel
Agile Delivery
Managing Projects
Test Driven Development
Agile Product Ownership
Risk Management on Agile Projects
An Appreciative Retrospective
chatgpt
Certification
Elastic Leadership
Enterprise DevOps
Principles of Lean-Agile Leadership
Development Value Streams
Artificial Intelligence
Software Development
Atlassian
Planning
QA
Lean Agile
Scrum Primer
Atlaassian
Process Improvement
RTE Role
AgileSparks
Logo
Enable registration in settings - general

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart