The horrible truth about software development estimation, and what to do about it

Facebook
Twitter
LinkedIn
Pinterest
WhatsApp

In recent years I’ve been working with many software development teams and almost all of them struggle with estimating the work. The energy spent on this and the frustration it causes should come to a halt. And so, in this short article, I combine knowledge gained by many people with my experience and explain how to address this.

A significant amount of time is spent on estimating the work required to build software. I’ve seen teams spending around two days every two weeks trying to understand how much the work will cost, with organizations spending valuable time of managers and experts haggling, pushing and fighting over estimations.

Does it work? Do they get the estimations right? No, they don’t. Why? Simply put, building software is complex. We think we know what’s ahead of us, but we just don’t. This is very difficult to grasp and accept. Requirements evolve. Design evolves. We gain understanding through the work. Things change all the time.

And so, as your expertise increases you come to the conclusion that, while it is usually possible to know the magnitude of order (hours/days/weeks), accurate estimation of the work in hours, days, weeks or months is almost impossible.

This is a great breakthrough, as once you understand this reality, that accurate estimation of software development is not possible, you can start moving forward.

What can be done? How can we have a prediction of when things will get done?

Reduce possibility of development going out of control

The key to the solution is to reduce the possibility of the development process getting out of control. Instead of trying to figure out how much effort it will take to develop features, we take two main measures to increase the predictability of our development process.

The first measure is keeping the batch size, the amount of requirements we develop, small enough. This is because the complexity of development increases at an exponential rate with the growth of the number of requirements.

The main question, therefore, when estimating work is not how much effort it is but rather is it in the right size. If it is too big we need to break it down to smaller pieces.

The right size may change from team to team according to several factors, but from my experience a software development team working with modern tools usually aims towards a few days per development item, something that can be demonstrated to a product manager.

Below see a cycle time control chart of a development team, produced from Jira Software. Each dot is one or more development items that ended on the time indicated by the X axis. The Y axis shows how long it took to develop that item. This team’s average cycle time is around 4 days, but from time to time There are items escaping that average – the team discusses these items in order to improve.

As written above, the first thing to do to handle the problem of estimating work items is to try and bring them down to a size the team is comfortable with. Whether it is 2, 3, or 4 days doesn’t matter – what matters is that it is more or less the team’s usual size, which gives plenty of space for changes during the actual development.

Increase development predictability

The second approach to adopt to increase development predictability is combining forces, working together as a team.

To handle the complexity of software development we use a whole team approach. The team plans its work and does it together. The approach of the team leader making the plan and then each team member getting an assignment that they work on alone doesn’t work.

Practically, what does “Teamwork” mean? It means planning together: the team looks at the scope of items, determines together whether they are small enough (see above), and decides on their forecast for the development period. The team then starts handling the various items. They take items according to priority and work on them together. Working on items together sometimes means working on two parallel streams of the same job, sometimes it means sitting together at one development machine (pairing). It means that according to need and priority people switch tasks to help their teammates, and in general, the team does whatever it takes to get the work done.

Here is an example of a team who moved from investing a lot of time (2 days per person per 2 weeks) on estimating to working together and avoiding exact estimation. The gray columns are how much was planned for a development period and the green columns are how much was actually done (the changes in throughput are due to personnel changes)

To summarize, instead of being heartbroken over spending endless time on estimation and not hitting the estimates, strive to break your work into smaller, lower complexity items and focus on teamwork. Software development work is thinking. And nothing beats thinking together.

(Photos by ThisisEngineering RAEng on Unsplash)

Subscribe for Email Updates:

Categories:

Tags:

Agile Exercises
Software Development Estimation
Lean Startup
An Appreciative Retrospective
Continuous Delivery
Scrum Values
Lean-Agile Budgeting
Pomodoro Technique
Story Slicing
Engineering Practices
Agile Games
SAFe Release Planning
Sprint Retrospectives
Quality Assurance
Agile Release Planning
Scrum
NIT
Agile Marketing
System Team
RSA
ScrumMaster Tales
Reading List
Lean Budgeting
Scrum Master Role
Agile Contracts Best Practices
Continuous Integration
Tips
Agile Mindset
Agile Project
GanttBan
Entrepreneurial Operating System®
The Kanban Method
Lean Agile Basics
Video
Lean Software Development
Agile Community
Professional Scrum Product Owner
Lean Risk Management
Risk-aware Product Development
Certified SAFe
Continuous Planning
Lean Agile
Coaching Agile Teams
System Integration Environments
Kaizen Workshop
BDD
Agile Product Ownership
Daily Scrum
LeSS
Jira Cloud
RTE Role
Product Management
Product Ownership
Kanban 101
Kanban
Risk Management in Kanban
Agile Games and Exercises
SA
Artificial Intelligence
Scrum Master
Code
predictability
Kaizen
Principles of Lean-Agile Leadership
EOS®
Agile and DevOps Journey
Team Flow
PI Planning
WIP
Nexus
Kanban Kickstart Example
Scrum Guide
Agile India
Nexus and Kanban
Slides
Professional Scrum with Kanban
Sprint Planning
ATDD vs. BDD
POPM
Scrum.org
Enterprise DevOps
User stories
Agile Risk Management
Agile for Embedded Systems
System Archetypes
Atlaassian
Keith Sawyer
Agile Product Development
Professional Scrum Master
Iterative Incremental Development
Covid19
Kanban Basics
Systems Thinking
Games and Exercises
Agile Program
Operational Value Stream
Limiting Work in Progress
lean agile change management
Built-In Quality
AI
Acceptance Test-Driven Development
Introduction to Test Driven Development
Legacy Code
Process Improvement
Large Scale Scrum
SPC
Effective Agile Retrospectives
speed at scale
Lean-Agile Software Development
Agile Outsourcing
Managing Projects
Retrospectives
Advanced Roadmaps
RTE
Rovo
Planning
Jira admin
Portfolio for Jira
Releases Using Lean
Continuous Deployment
transformation
Nexus vs SAFe
ATDD
Agile Development
Agile Delivery
TDD
Nexus and SAFe
Change Management
AgileSparks
Agile Basics
Certification
Legacy Enterprise
Accelerate Value Delivery At Scale
Lean and Agile Techniques
Scrum and XP
IT Operations
PI Objectives
Sprint Iteration
Agile
SAFe DevOps
Hybrid Work
Agile in the Enterprise
AI Artificial Intelligence
Implementing SAFe
Manage Budget Creation
Program Increment
QA
Kanban Game
Achieve Business Agility
DevOps
Introduction to ATDD
Spotify
ROI
Agile Testing Practices
Rapid RTC
Agile Project Management
Software Development
What Is Kanban
Scrum With Kanban
Jira Plans
Jira
Lean and Agile Principles and Practices
Managing Risk on Agile Projects
Agility
Agile Release Management
Release Train Engineer
Applying Agile Methodology
speed @ scale
Agile Israel
Lean Agile Organization
ART Success
Implementation of Lean and Agile
Frameworks
chatgpt
Agile Israel Events
A Kanban System for Software Engineering
Test Driven Development
Atlassian
ARTs
LPM
LAB
agileisrael
Self-organization
Risk Management on Agile Projects
Scrum Primer
Value Streams
Confluence
Presentation
Lean Agile Management
Agile Techniques
ALM Tools
Tools
Nexus Integration Team
Perfection Game
Agile Assembly Architecture
Elastic Leadership
Webinar
Amdocs
Scaled Agile Framework
Continuous Improvement
Business Agility
Development Value Streams
SAFe
The Agile Coach
AgileSparks
Logo
Enable registration in settings - general

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart