The horrible truth about software development estimation, and what to do about it

Facebook
Twitter
LinkedIn
Pinterest
WhatsApp

In recent years I’ve been working with many software development teams and almost all of them struggle with estimating the work. The energy spent on this and the frustration it causes should come to a halt. And so, in this short article, I combine knowledge gained by many people with my experience and explain how to address this.

A significant amount of time is spent on estimating the work required to build software. I’ve seen teams spending around two days every two weeks trying to understand how much the work will cost, with organizations spending valuable time of managers and experts haggling, pushing and fighting over estimations.

Does it work? Do they get the estimations right? No, they don’t. Why? Simply put, building software is complex. We think we know what’s ahead of us, but we just don’t. This is very difficult to grasp and accept. Requirements evolve. Design evolves. We gain understanding through the work. Things change all the time.

And so, as your expertise increases you come to the conclusion that, while it is usually possible to know the magnitude of order (hours/days/weeks), accurate estimation of the work in hours, days, weeks or months is almost impossible.

This is a great breakthrough, as once you understand this reality, that accurate estimation of software development is not possible, you can start moving forward.

What can be done? How can we have a prediction of when things will get done?

Reduce possibility of development going out of control

The key to the solution is to reduce the possibility of the development process getting out of control. Instead of trying to figure out how much effort it will take to develop features, we take two main measures to increase the predictability of our development process.

The first measure is keeping the batch size, the amount of requirements we develop, small enough. This is because the complexity of development increases at an exponential rate with the growth of the number of requirements.

The main question, therefore, when estimating work is not how much effort it is but rather is it in the right size. If it is too big we need to break it down to smaller pieces.

The right size may change from team to team according to several factors, but from my experience a software development team working with modern tools usually aims towards a few days per development item, something that can be demonstrated to a product manager.

Below see a cycle time control chart of a development team, produced from Jira Software. Each dot is one or more development items that ended on the time indicated by the X axis. The Y axis shows how long it took to develop that item. This team’s average cycle time is around 4 days, but from time to time There are items escaping that average – the team discusses these items in order to improve.

As written above, the first thing to do to handle the problem of estimating work items is to try and bring them down to a size the team is comfortable with. Whether it is 2, 3, or 4 days doesn’t matter – what matters is that it is more or less the team’s usual size, which gives plenty of space for changes during the actual development.

Increase development predictability

The second approach to adopt to increase development predictability is combining forces, working together as a team.

To handle the complexity of software development we use a whole team approach. The team plans its work and does it together. The approach of the team leader making the plan and then each team member getting an assignment that they work on alone doesn’t work.

Practically, what does “Teamwork” mean? It means planning together: the team looks at the scope of items, determines together whether they are small enough (see above), and decides on their forecast for the development period. The team then starts handling the various items. They take items according to priority and work on them together. Working on items together sometimes means working on two parallel streams of the same job, sometimes it means sitting together at one development machine (pairing). It means that according to need and priority people switch tasks to help their teammates, and in general, the team does whatever it takes to get the work done.

Here is an example of a team who moved from investing a lot of time (2 days per person per 2 weeks) on estimating to working together and avoiding exact estimation. The gray columns are how much was planned for a development period and the green columns are how much was actually done (the changes in throughput are due to personnel changes)

To summarize, instead of being heartbroken over spending endless time on estimation and not hitting the estimates, strive to break your work into smaller, lower complexity items and focus on teamwork. Software development work is thinking. And nothing beats thinking together.

(Photos by ThisisEngineering RAEng on Unsplash)

Subscribe for Email Updates:

Categories:

Tags:

agileisrael
Lean and Agile Principles and Practices
Atlaassian
Managing Projects
Product Ownership
speed @ scale
Jira
Systems Thinking
Built-In Quality
Limiting Work in Progress
QA
Story Slicing
Professional Scrum Master
RSA
Agile Games and Exercises
Lean Agile Organization
NIT
Scrum Primer
Development Value Streams
SAFe
Agile Product Ownership
Kanban
Scrum Values
Kanban Game
Enterprise DevOps
Continuous Integration
Agile Mindset
Sprint Retrospectives
SAFe Release Planning
Managing Risk on Agile Projects
Lean Software Development
Elastic Leadership
TDD
Agile
DevOps
Change Management
Agile India
Agile Risk Management
Business Agility
ATDD vs. BDD
Agile Techniques
Kaizen Workshop
Retrospectives
Lean Budgeting
IT Operations
Lean Agile Management
Agile Delivery
Agile Marketing
speed at scale
ALM Tools
Coaching Agile Teams
Agile Project Management
Scrum Master
Software Development
Continuous Improvement
Scaled Agile Framework
LPM
PI Objectives
Scrum and XP
Frameworks
Lean-Agile Software Development
Agile Exercises
Tips
ART Success
RTE
Agile Product Development
Legacy Enterprise
Agility
Lean Risk Management
Lean and Agile Techniques
transformation
Nexus Integration Team
Operational Value Stream
The Agile Coach
RTE Role
Continuous Delivery
Advanced Roadmaps
Kanban Kickstart Example
LAB
Iterative Incremental Development
Risk Management in Kanban
Agile Israel Events
Lean Agile
Lean Agile Basics
Effective Agile Retrospectives
Jira admin
Kanban 101
Kanban Basics
SPC
Nexus
Scrum Master Role
AI Artificial Intelligence
Planning
Code
Risk-aware Product Development
Pomodoro Technique
Acceptance Test-Driven Development
Agile Program
ROI
Amdocs
Lean-Agile Budgeting
System Integration Environments
AgileSparks
Legacy Code
Scrum
Sprint Planning
Risk Management on Agile Projects
ARTs
PI Planning
Value Streams
Agile Release Management
Applying Agile Methodology
User stories
Jira Plans
lean agile change management
Scrum With Kanban
Self-organization
BDD
SA
Keith Sawyer
Hybrid Work
chatgpt
Agile Development
Agile Basics
POPM
Professional Scrum Product Owner
EOS®
Presentation
Software Development Estimation
Agile Testing Practices
Games and Exercises
Scrum.org
WIP
Agile and DevOps Journey
Team Flow
Release Train Engineer
Implementing SAFe
Large Scale Scrum
Perfection Game
Video
Agile for Embedded Systems
LeSS
Confluence
Product Management
System Team
Implementation of Lean and Agile
AI
Agile Community
Engineering Practices
Process Improvement
Continuous Planning
Nexus vs SAFe
Agile in the Enterprise
Jira Cloud
Tools
Covid19
Sprint Iteration
Artificial Intelligence
Lean Agile Leadership
The Kanban Method
ATDD
Accelerate Value Delivery At Scale
Agile Contracts Best Practices
GanttBan
SAFe DevOps
Continuous Deployment
Certification
Test Driven Development
Certified SAFe
Agile Outsourcing
What Is Kanban
System Archetypes
Rapid RTC
predictability
Daily Scrum
Principles of Lean-Agile Leadership
ScrumMaster Tales
Agile Games
Portfolio for Jira
Agile Assembly Architecture
Introduction to ATDD
Achieve Business Agility
Atlassian
Releases Using Lean
Agile Project
Nexus and SAFe
Webinar
Scrum Guide
Nexus and Kanban
An Appreciative Retrospective
Spotify
Lean Startup
Manage Budget Creation
Entrepreneurial Operating System®
Slides
Program Increment
Rovo
Introduction to Test Driven Development
Kaizen
Agile Release Planning
A Kanban System for Software Engineering
Quality Assurance
Agile Israel
Reading List
AgileSparks
Logo
Enable registration in settings - general

Contact Us

Request for additional information and prices

AgileSparks Newsletter

Subscribe to our newsletter, and stay updated on the latest Agile news and events

This website uses Cookies to provide a better experience
Shopping cart